The general contractor continued work on the floor of Room 545 and the installation of ceiling grid in the hallways.
The construction cleaning contractor continued cleaning restrooms on all floors and commenced cleaning stairwells.
The electrical contractor continued installing new light fixtures in the front hallway on the 6th Floor.
The elevator contractor removed the protective film on Elevator 7.
The furniture vendor continued installing built-in cabinets in the lounge on 7th Floor.
The network wiring contractor continued new data wiring on the 6th Floor.
The painting contractor painted the ceiling support bases for the new light fixtures in the 1st Floor lobby.
Window glass contractor replaced the broken window in the 7th Floor lounge and several windows on the 3rd and 4th Floors.
Facility Services continued minor repairs on various floors.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS
The general contractor poured concrete for the riser seating in Auditorium B and entry stairs in Auditorium A.
The electrical contractor started running conduit from the electrical room to the AV room.
EXTERIOR/LANDSCAPING:
Facility Services tested the sprinkler operation for the landscaping in front of 1542 Tulane Avenue .
DENTAL SCHOOL
6th & 8th FLOOR LAB RENOVATIONS:
The general contractor framed the main doorway for Suite 8405 and framed the exterior windows.
LIBRARY
COMMONS
The contractor started installation of the ceiling grid in the smaller multimedia room.
Siemens ran poly tubing to the thermostat locations.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
LSUHSC has been granted beneficial occupancy of the laboratory that was relocated from the 6th Floor to make room for the Cohn Learning Center .This means that lab operations can be moved into the space and research activities can begin.
The mechanical subcontractor insulated chilled and heating hot water lines on the east side of the 1st Floor.
They finished tying in the supply and outside air duct on the west side of the 1st Floor.
Pipe for the new medical air and vacuum is being installed on the 2nd Floor.
Crews continue to install the exhaust lines for the med gas bottle room on the 6th Floor.
The electrical subcontractor pulled ground wire for the cable tray and switchgear.
They ran the feeders into the new switchgear on the 2nd Floor.
They installed wire for the fire alarm devices on the south side of the 6th Floor.
The iron subcontractor finished welding the granite curtain wall brackets on the exterior stairwell tower.
The fireproofing subcontractor primed welds on the 3rd – 6th Floors of the stairwell tower.
The contractor grouted restroom wall tiles on the east side of the 6th Floor.
They continued installing CMU on the 1st Floor, southeast corner.
MEB
2nd FLOOR RENOVATIONS:
The contractor finished placing sheetrock on the interior walls by Medical Center Stores.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor installed plywood on the exterior temporary wall, which will remain in place while the old curtain wall is removed and the new curtain wall is installed.
The contractor removed existing 2x4 light fixtures and wall mount light fixtures from the Perdido St. and Bolivar St. corner.