The general contractor completed installing carpet in Room 545.
They completed installing ceiling tiles in the front hallway of the 5th Floor and began installing ceiling tiles in the 4th Floor lounge.
The painting contractor continued work in the rear stairwell.
Facility Services continued minor repairs on various floors.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The general contractor installed additional ceiling grid in Auditorium A.Two rows remain to be completed.
The contractor installed foam insulation inside the new door frames.
The electrical contractor installed additional conduit for the electrical panel power feeds.
DENTAL
6th & 8th FLOOR LABORATORY RENOVATIONS:
The general contractor installed insulation on the exterior walls in Rooms 8405B and 8405K.
The contractor installed framing support rods for all walls in Suite 8405 .
EXTERIOR/LANDSCAPING:
Facility Services removed old vegetation in front of the Resource Center .
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor set water fountains on the 6th Floor, S. Prieur side and installed VAVs on the 6th Floor Gravier/Bolivar St. side.
The electrical subcontractor ran conduit for Panel LA6A, wired domestic water pumps to Panel AC2A, wired Riser B to the switchgear breakers on the 2nd Floor, installed and wired Panel 2AB on the 2nd Floor and installed cable tray on the 2nd Floor, Gravier hallway side.
The contractor installed ceiling grid on the 6th Floor on the Gravier/S. Prieur side.
They grouted wall tile in the 6th Floor restrooms.
Crews primed the marker boards in the 6th Floor simulation rooms.
Sheetrock on the 2nd Floor CSRB side is being floated.
They installed CMU on the front of the 1st Floor lobby by Elevators 1 and 4.
A crew plastered the restroom on the 1st Floor, Bolivar/CSRB side.
Floor tile is being installed in the restrooms on the 1st Floor, S. Prieur Street side.
LIBRARY
COMMONS:
The contractor installed the frieze.
The contractor continued installation of wood panel supports on the columns.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The contractor removed the ceiling grid in the administrative area.
MEB
2ND FLOOR LOBBY RENOVATIONS:
The contractor installed sprinkler main piping on the Bolivar St. side of the lobby.
MEB
MDL 6 RENOVATIONS:
The contractor installed piping for hot/cold water and drainage in the 3rd Floor ceiling for MDL 6.
The contractor installed sheetrock above the movable partitions.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor removed the mailboxes.
The contractor installed wood nailers for roof flashing above the walkway.