The electrical contractor continued installing new light fixtures in the conference rooms on the 2nd and 3rd Floors.
The elevator contractor continued removing the protective film from Elevator 3.
The general contractor continued drywall taping and preparation in Room 545.
The painting contractor continued painting the front stairwell on the Charity end of the hall.
The network wiring contractor continued wiring new drops on the 5th Floor.
Facility Services sealed old exhaust duct wall penetrations on the exterior walls facing the Lakeside Lot and continued making minor repairs on various floors.
Electricians ran new conduit for additional exterior lighting that will be installed at the rear of the building.
DENTAL
CAMPUS AUDITORIUMS A & B RENOVATIONS:
The contractor completed the concrete finishing work for the stairs in Auditorium B.
The mechanical contractor installed the drain line to the AHU for Auditorium B.
DENTAL
6th & 8th FLOOR LABORATORY RENOVATIONS:
The electrical contractor connected wiring for the junction boxes above the ceiling in Suite 8405 .
EXTERIOR/LANDSCAPING:
LSUHSC Facility Services crews performed landscape maintenance around the downtown campus.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor installed more thermostats on the 6th Floor.
They continued demolishing ductwork and water pipes in the 6th Floor lab and glass pipe on the 2nd Floor.
Heating hot water and chilled water pipes on the Bolivar St. side of the 1st Floor are being insulated.
The electrical subcontractor continued to remove the old conduits in the 6th Floor lab.
They ran conduit to ATS 1 and 2 from the 2nd Floor to the new switchgear and installed conduit for the lights and exhaust fans in the stairwell.
The sprinkler subcontractor installed stand pipe in the stairwell sprinklers.
The contractor taped and floated sheetrock in the 6th Floor simulation rooms.
Crews installed metal studs and sheetrock for the fur down on the S. Prieur/Gravier St. side of the 6th Floor.
They also installed metal studs and sheetrock on the 2nd Floor and metal lathe on the 1st Floor.
The CMU wall on the 1st Floor is being plastered.
Wall tile is being installed in the restrooms on the 1st Floor.
They pressure washed the new stairwell.
LIBRARY
COMMONS:
LSU electricians installed light fixture supports in the ceiling near the windows.
MEB
2ND FLOOR LOBBY RENOVATIONS:
The sprinkler subcontractor installed sprinkler pipe on the Roman St. side of the lobby.
MEB
MDL 6 RENOVATIONS:
The contractor removed the remaining VCT tiles from the main MDL room.
They finished capping existing plumbing below the floor in the main MDL room.
Existing receptacles in the main MDL room were disconnected and capped.
The contractor de-installed the existing LCD panels and projector screens from the main MDL room.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor removed the existing frame where the temporary wall was built and installed two vertical frames near the double sliding door.