Louisiana State University Health Sciences Center Administration & Finance
 

Monday, December 8, 2008

 

1542 TULANE AVE.:

  • The elevator contractor lowered the audible floor announcement volume in the elevator cabs.  
  • The furniture vendor installed new cabinets in the 5th Floor lounge and set-up conference room furniture in Rooms 524 and 544.
  • The general contractor continued drywall sanding and priming in Room 545.
  • The painting contractor began painting the front stairwell on the Claiborne Avenue end of the front hallway.
  • The terrazzo contractor is making repairs to the cove base in the front hallways on the 4th through the 7th Floors.
  • LSUHSC Facility Services replaced two fan coil units in Rooms 516 and 517 and continued minor repairs on various floors.  

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The contractor installed metal framing for the audiovisual room.  

 

DENTAL CAMPUS 6TH AND 8TH FLOOR LAB RENOVATIONS :

  • The contractor installed sheetrock on the southwest walls. 

 

EXTERIOR/LANDSCAPING:

  • Facility Services installed landscape edging and mulched the planting beds in front of the Resource Center .

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The mechanical subcontractor set plumbing fixtures on the CSRB side of the 6th Floor.
    • They demolished old storm drain that was run above the ceiling on the 6th Floor, Gravier/Bolivar St. side.
    • Storm drain pipe is being installed in the new stairwell from Floors 5 and 6.
  • The electrical subcontractor installed Panel LA6A on the 6th Floor.
    • They ran conduit for lights on the 6th Floor, Gravier/Bolivar St. side.
    • The electricians wired Panel 2AC to the switchgear on the 2nd Floor, wired the switchgear to Panel 2AC2A, and installed the emergency junction box on top of the switchgear.
    • Entergy installed electrical service to the building.  
  • The fireproofing subcontractor painted the main structure beams on the 5th Floor of the new exterior stairwell.
  • The contractor taped and floated sheetrock and installed corner bead on the 6th Floor.
    • Projection mount poles were installed on the 6th Floor.
    • Crews installed studs and sheetrock on the 2nd Floor by the new stairwell on the Gravier St. side.
    • They installed metal studs and sheetrock on the 2nd Floor between the new fire pump and the medical air/vacuum pumps.
    • Crews continued to plaster the 1st Floor CMU wall on the S. Prieur Street side and install wall tile in the restrooms on the 1st Floor, S. Prieur Street side.

 

LIBRARY COMMONS:              

  • The contractor grouted wall tiles on the frieze wall and installed floor tiles near the Library entrance. 
  • The contractor installed HVAC diffusers near the window walls.   

 

MEB 2ND FLOOR LOBBY RENOVATIONS:

  • The sprinkler subcontractor installed sprinkler pipe along the walls by the lecture halls and in the middle of the ceiling on the Roman Street side.
  • The contractor removed ceiling remnants on the Bolivar Street side.

 

MEB MDL 6 RENOVATIONS:

  • The contractor raised the steel support for the new partition track in the MDL room.
  • The contractor removed floor tiles from Rooms 4114A and 4121A.

 

RESIDENCE HALL LOBBY EXPANSION:

  • The contractor installed three vertical mullions in front of the temporary wall.
  • The contractor painted the plywood for the temporary wall.

 

MEB 6109 & 6148 LAB RENOVATION:

  • The contractor installed new cove base in both rooms.