1542 TULANE AVE.:

  • The general contractor completed painting the walls in Room 443 and began installing the ceiling grid. 
    • Wall framing in the 2nd Floor lounge was completed and drywall installation started on the ceiling fur down. 
    • The build out of the 1st Floor lounge commenced and wall repair continued in the 2nd and 3rd Floor offices.
  • The lighting contractor installed new light fixtures in Rooms 111, 111A and 111B. 
  • Facility Services continued painting offices and hallways on the 4th Floor.

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The electrical contractor installed trim rings for the recessed can light fixtures in Auditoriums A and B.

 

DENTAL 6th & 8th FLOOR RENOVATIONS:

  • The contractor sanded and placed the second skim coat on the walls in 6333, 6335, and Suite 8405 .

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued installing irrigation piping and sprinklers in the back of the Resource Center .

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:    

  • The mechanical subcontractor began installing control wire to AHU 6-1.
    • They tested medical gas outlet boxes in the simulation rooms.
    • Supply air grills were installed on the CSRB side of the 6th Floor.
    • Crews continued insulating heating hot water lines on the 6th Floor, Bolivar St. side.
  • The contractor installed bathroom partitions and drywall on the Bolivar St. side of the 6th Floor.
    • A crew installed ceiling tiles on 6th Floor, CSRB side.
    • Ceiling grid was installed on the S. Prieur St. side of the 6th Floor.
    • They continued painting the exterior stairwell.
  • The contractor switched the power sources of Riser B which serves the S. Prieur St. electrical receptacles and lights to the new switchgear.

 

LIBRARY COMMONS:

  • The contractor installed sheetrock at the stairwell and in the small multi media room.
  • They taped and floated walls in the Library Commons. 
  • LSUHSC electricians continued installing light fixtures in the cafe.

 

MEB 2ND FLOOR LOBBY RENOVATIONS:

  • The contractor installed ceiling grid in the center of the lobby.

 

MEB MDL 6 RENOVATIONS

  • The contractor continued relocating sprinkler heads in the main MDL room.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The general contractor completed framing the new walls. 
  • The electrical contractor continued to run conduit in the laboratory area. 
  • The mechanical contractor capped hot/cold/deionized water lines on the 4th Floor below the Pharmacology labs.

     

RESIDENCE HALL LOBBY EXPANSION: 

  • The contractor installed exterior vertical mullion on the Perdido Street side of the lobby.