1542 TULANE AVE. :

  • The general contractor continued taping and floating the drywall in the 2nd Floor lounge and framing walls and fur downs in the 1st Floor lounge. 
  • The cleaning contractor continued cleaning restrooms, windows, hallways and floors on the 4th Floor. 
  • The furniture vendor installed the new reception desk in the front lobby. 
  • The mechanical contractor continued piping new fan coil units in rooms on the 2nd and 3rd Floors. 
  • The network wiring contractor commenced installation of new network drops on the 4th Floor. 
  • The painting contractor continued painting Room 109/109A and 32 exterior and stairwell doors. 
  • Facility Services continued painting offices and hallways on the 4th Floor, continued minor repairs on the 4th Floor, and commenced installing the new electrical conduit for exterior lighting by the shipping and receiving entrance.

 

DENTAL CAMPUS AUDITORIUMS A & B RENOVATIONS:

  • The contractor continued installing the door frames.

 

DENTAL 6th & 8th FLOOR RENOVATIONS:

  • The general contractor installed the ceiling grid in Rooms 8405Band 8405K and began installation the ceiling grid in Room 6335. 
  • The contractor set the remaining light fixtures in Suite 8405 .

 

EXTERIOR/LANDSCAPING:

  • Contractor continued setting the brick pavers for the new sidewalk along Gravier St. and at the corner of Gravier St. and S. Claiborne Ave.  

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The contractor completed installing the exterior signage.
    • They removed the floor from the elevator lobby on the 6th Floor, Bolivar Street side.
    • Crews continued installing restroom partitions in the 6th Floor restrooms on the S. Prieur Street side.
    • They continued installing sheetrock on the 6th Floor Gravier/Bolivar Street side.
    • The installation of wall tile on the Gravier St./Bolivar St. side of the 1st Floor was completed. 
  • The sprinkler subcontractor continued piping from the fire pump to distribution lines in the 2nd Floor stairwells.  
  • The electrical subcontractor pulled additional fire alarm wire; installed conduit for lights, installed lights in the mechanical room and installed wire to the VAVs on the Bolivar St. side of the 6th Floor. 
  • The mechanical subcontractor is setting sinks in the 6th Floor,  Bolivar Street side restrooms.
    • They installed a thermostat in electrical room on the 6th Floor.
    • The installation of return air ducts, supply duct to the VAV boxes, and supply grilles on the Bolivar St. side of the 6th Floor Bolivar Street is proceeding.

       

LIBRARY COMMONS:

  • The contractor continued to tape and float drywall in various areas.

 

MEB MDL 6 RENOVATIONS:

  • The contractor began leveling the flooring in the main lab.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The general contractor continued to install sheetrock and insulation in the laboratory area. 
  • The electrical contractor installed additional conduit in the laboratory area.

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The contractor primed the fur down in the lobby between the A & B Towers .
  • The contractor installed horizontal exterior mullions.

 

CSRB AUTOMATIC WALKWAY INSTALLTION: