Louisiana State University Health Sciences Center Administration & Finance
 

Friday, January 30, 2009

 

1542 TULANE AVE. :

  • The mechanical contractor continued piping new fan coil units in rooms on the 2nd and 3rd Floors. 
  • The network wiring contractor continued installation of new network drops on the 4th Floor. 
  • The painting contractor continued painting exterior and stairwell doors. 
  • Facility Services continued painting offices and hallways on the 4th Floor and continued installing the new electrical conduit for exterior lighting by the Shipping and Receiving entrance.

 

DENTAL 6th & 8th FLOOR RENOVATIONS:

  • The general contractor installed ceiling grid in Rooms 6333 and 6335, and installed corner guards around columns in Room 8405B.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The contractor installed curtain wall metal on the 1st Floor of the new exterior stairwell, on the Bolivar Street side of the structure. 
    • Crews continued removing the old floor from the elevator lobby on the 6th Floor.
    • Marker board trays were installed on the 6th Floor.
    • They continued installing sheetrock and door frames on the 6th Floor, Gravier St./Bolivar St. side and grouting the wall tile on the 1st floor.
  • The sprinkler subcontractor began piping the distribution lines in the new stairwell. 
  • The mechanical subcontractor installed storm drain pipe in the new stairwell on the 2nd and 3rd Floors.
    • They installed fire dampers on the 2nd Floor, CSRB side.
    • Crews continue to insulate heating hot water lines on the 6th Floor, Bolivar St. side.

 

LIBRARY COMMONS:

  • The contractor continued to tape and float drywall in various areas.

 

MEB MDL 6 RENOVATIONS:

  • The contractor continued leveling the concrete subflooring in the main lab.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The general contractor continued to install sheetrock and insulation in the laboratory area. 
  • The electrical contractor installed additional conduit in the laboratory area.

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The interior contractor installed sheetrock for the fur down in the Perdido St./Bolivar St. corner of the lobby. 
  • The enclosure contractor continued installed the horizontal exterior mullions.
    • They installed break metal track for the underside of the storefront and caulked the Perdido St. perimeter.
    • They have begun to remove the temporary wall.

 

RESIDENCE HALL WALKWAY RESURFACING:

  • The contractor applied the first coat of stain on the walkway surface.