The mechanical contractor continued piping new fan coil units in rooms on the 2nd and 3rd Floors.
The network wiring contractor continued installation of new network drops on the 4th Floor.
The painting contractor continued painting exterior and stairwell doors.
Facility Services continued painting offices and hallways on the 4th Floor and continued installing the new electrical conduit for exterior lighting by the Shipping and Receiving entrance.
DENTAL
6th & 8th FLOOR RENOVATIONS:
The general contractor installed ceiling grid in Rooms 6333 and 6335, and installed corner guards around columns in Room 8405B.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The contractor installed curtain wall metal on the 1st Floor of the new exterior stairwell, on the Bolivar Street side of the structure.
Crews continued removing the old floor from the elevator lobby on the 6th Floor.
Marker board trays were installed on the 6th Floor.
They continued installing sheetrock and door frames on the 6th Floor, Gravier St./Bolivar St. side and grouting the wall tile on the 1st floor.
The sprinkler subcontractor began piping the distribution lines in the new stairwell.
The mechanical subcontractor installed storm drain pipe in the new stairwell on the 2nd and 3rd Floors.
They installed fire dampers on the 2nd Floor, CSRB side.
Crews continue to insulate heating hot water lines on the 6th Floor, Bolivar St. side.
LIBRARY
COMMONS:
The contractor continued to tape and float drywall in various areas.
MEB
MDL 6 RENOVATIONS:
The contractor continued leveling the concrete subflooring in the main lab.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The general contractor continued to install sheetrock and insulation in the laboratory area.
The electrical contractor installed additional conduit in the laboratory area.
RESIDENCE
HALL LOBBY EXPANSION:
The interior contractor installed sheetrock for the fur down in the Perdido St./Bolivar St. corner of the lobby.
The enclosure contractor continued installed the horizontal exterior mullions.
They installed break metal track for the underside of the storefront and caulked the Perdido St. perimeter.
They have begun to remove the temporary wall.
RESIDENCE
HALL WALKWAY RESURFACING:
The contractor applied the first coat of stain on the walkway surface.