Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, January 6, 2009

 

1542 TULANE AVE. :

  • The general contractor installed drywall for Room 443, continued paint removal in the auditorium, installed a new wall in Room 345 and continued patching holes on the 3rd Floor. 
  • The flooring contractor set-up for carpet installation on the 4th Floor. 
  • The painting contractor completed painting the center stairwell from the 5th to 8th Floor. 
  • Facility Services continued installing door stops, adjusting doors, and installing new room numbers on the 4th Floor.

 

DENTAL 6th & 8th FLOOR LABORATORY RENOVATIONS:

  • The mechanical contractor installed the supply duct outlet taps for the ductwork in 8405A.

 

EXTERIOR/LANDSCAPING:

  • Facility Services installed the landscape edging, continued finish grading and continued installing plants in front of the Resource Center .

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The mechanical subcontractor completed installing and tested new chilled water lines to the 1st Floor AHU on the Bolivar Street side.
  • The electrical subcontractor installed the first floor buss duct tap on the Bolivar Street side.
  • The sprinkler subcontractor installed sprinkler heads on the 6th Floor, Bolivar Street side.
  • The contractor installed studs on the 6th Floor, Gravier Street side.
    • They installed ceiling grid on the 6th Floor in the center hallway and continued fireproofing the beams on the 4th – 6th Floors of the new exterior stairwell.

 

LIBRARY COMMONS:

  • The contractor continued installing custom column covers.
  • Crews installed ceiling tile in the café area. 

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The contractor completed removing all ceilings.
  • The electrical subcontractor completed removing lights in the laboratory and administrative area. 

 

MEB MDL 6 RENOVATIONS:

  • The contractor framed the wall for the partition storage room. 
  • The contractor installed the partition track in the main MDL room. 

 

RESIDENCE HALL LOBBY EXPANSION:

  • The contractor installed HVAC diffuser boxes and flex duct on the Perdido and Bolivar Street side of the lobby.