Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, January 8, 2009

 

1542 TULANE AVE. :

  • The general contractor continued removing old paint in the auditorium, patching holes on the 2nd and 3rd Floors, and installing drywall in Room 443.
    • They began working on the build-out of the 2nd Floor lounge.
  • Facility Services continued removing old striping in the Lakeside Lot. 

 

EXTERIOR/LANDSCAPING:

  • Facility Services completed installing plants and spreading mulch in front of the Resource Center .

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The mechanical subcontractor installed heating hot water lines to the 6th Floor, Bolivar Street Side VAV.
    • They installed supply duct on the Bolivar St. side of the 6th Floor.
    • A crew insulated chill water lines is the same area.
    • Fixtures were installed on the 1st Floor, S. Prieur Street side.
  • The electrical subcontractor roughed in junction boxes on the 6th Floor, Bolivar Street side and installed light fixtures in the hallway between the simulation rooms on the 6th Floor.
  • The sprinkler subcontractor installed sprinkler heads on the 6th Floor, Bolivar Street Side between the simulation rooms. 
  • The contractor completed installing access panels on the S. Prieur Street side of the 3rd and 7th Floors.
    • A crew installed studs on the 6th Floor, Gravier/Bolivar Street Side.
    • Others installed wall tile on the 1st Floor, S. Prieur Street side.
    • They continued fireproofing the beams on the 1st through 6th Floors of the exterior stairwell.

 

LIBRARY COMMONS:

  • Work continued on the installation of the custom wood column covers.
  • Branch HVAC ductwork was installed in the large multimedia room. 
  • New sprinkler heads have been installed in the window seating area and the multimedia rooms.     

 

MEB 2ND FLOOR LOBBY RENOVATIONS:

  • The flooring contractor continued installing floor tile on the Bolivar Street side.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The electrical subcontractor continued demolition and started running new conduit in the laboratory area. 
  • The general contractor removed construction debris.

 

MEB MDL 6 RENOVATIONS: 

  • The contractor installed ceiling grid in the main MDL room and installed sheetrock for the partition storage room.

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The contractor began the installation of new ceiling grid in the lobby between Towers A and B.