The general contractor continued patching holes in offices on the 2nd and 3rd Floors.
The mechanical contractor continued piping new fan coil units on the 2nd and 3rd Floors.
The painting contractor continued priming and began painting offices on the 3rd Floor.
Facility Services continued repairs on the 3rd Floor, connecting electrical service for fan coil units, and installing new door hardware on the 2nd and 3rd Floors.
EXTERIOR/LANDSCAPING:
The contractor laid sod in the lot at the corner of Gravier St. and S. Claiborne Ave.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The mechanical subcontractor installed fuel lines in Room 901 and ran control wiring to the 1st Floor air handling units.
The contractor primed the walls of the simulation room on the Bolivar St. side of the 6th Floor.
They painted the lounge area on the 6th Floor, Gravier St. side.
Crews installed the fire wall on the 5th Floor, Gravier Street side, installed tile floors in the restrooms on the Bolivar St. side of the 1st Floor and began stripping the 1st Floor lobby floors.
The electrical contractor installed cable tray on the 6th Floor, provided power to the rollup door on the 6th Floor, and installed a junction box in Room 901 on the 9th floor.