  • The furniture contractor began installing the new cabinetry in the 3rd Floor lounge.
  • The mechanical contractor continued installing new fan coil units on the 3rd Floor.
    • They started work on the plumbing for the 2nd Floor lounge.
  • The parking garage contractor completed painting the pavement marking in the parking garage. 
  • Facility Services continued repairs on the 1st and 3rd Floors, painting hallways on the 3rd Floor, connecting electrical service for fan coil units, and installing new door hardware on the 2nd Floor.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:   

  • The mechanical contractor installed fuel pipes on the roof and installed control wire to the AHU located on the 1st Floor, Bolivar Street side. 
  • The contractor painted the computer lounge on the 6th Floor.
    • They installed ceiling grid on the 6th Floor in a simulation room.
    • A crew installed closers and kick plates for new doors on the 1st Floor, CSRB/S. Prieur Street side;
  • The contractor continued patching the ceiling on the 1st Floor, S. Prieur Street side, installing wall tile in restrooms on the 1st Floor, Bolivar/CSRB side and installing mullions and corners on the 1st through 6th Floors of the new stairwell.

 

LIBRARY COMMONS:

  • The contractor continued priming the walls preparing for hanging wallpaper. 
  • The contractor continued installing the display case in the elevator lobby.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor installed break metal around the Lecture Hall doors and continued installing break metal around the elevator doors. 

 

MEB MDL 6 RENOVATIONS:

  • The network wiring contractor terminated data ports.
  • The electrical contractor continued installing light switches and receptacles.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The contractor primed and patched the walls in the laboratory area.

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The contractor continued installing ceiling track in the expanded lobby area.
  • The interior contractor continued demolition of the ceiling and lighting in the back lobby on Perdido St. and S. Roman St .

 

DENTAL 6th & 8th FLOOR LAB RENOVATIONS:

  • The contractor installed one side of base cabinets and countertops for the peninsula lab benches in Rooms 8405A and 8405B.

 

DENTAL SCHOOL BOILER INSTALLATION:

  • The contractor installed pipe hangers and piping for the gas, steam, and water supply.