The general contractor continued taping and floating the drywall in the 2nd Floor lounge and framing walls and fur downs in the 1st Floor lounge.
They began rerouting sprinkler piping in both lounges.
Work continued patching holes in offices on the 3rd Floor.
The furniture vendor arranged furniture in offices on the 4th Floor.
The mechanical contractor continued piping new fan coil units on the 2nd and 3rd Floors.
The network wiring contractor continued installation of new network drops on the 4th Floor.
The painting contractor continued painting exterior and stairwell doors.
Facility Services continued painting offices and hallways on the 4th Floor and installing the new electrical conduit for exterior lighting by the Shipping and Seceiving entrance.
DENTAL
6th & 8th FLOOR RENOVATIONS:
The contractor painted the interior rooms on the 8th Floor.
EXTERIOR/LANDSCAPING:
Facility Services planted shrubs in the planting beds on the Gravier St. side of the Resource Center .
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The contractor installed storefront glass located near the new stairwell on the 6th Floor.
They installed the mud bed for tile in the elevator lobby on the 6th Floor.
The sprinkler subcontractor continued piping at the new fire pump.
The contractor continued hanging sheetrock and running electrical conduits in the old 6th Floor lab area.
The electrical contractor started installed receptacles in the simulation labs.
The contractor installed doors on the first floor.
LIBRARY
COMMONS:
The contractor installed automatic doors at the main library entrance.
LSUHSC electricians began installing light fixture supports above the coffee kiosk.
LSUHSC personnel installed security cameras.
MEB
MDL 6 RENOVATIONS:
The contractor began installing floor tiles in the main lab area.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The general contractor completed the sheetrock installation and insulation in the laboratory area.
They began taping and floating the new sheetrock.
The electrical contractor completed the installation of conduit in the administration area.
The mechanical contractor installed waste water pipes below the laboratory area.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor continued to paint the exposed sprinkler pipe.
The contractor removed electrical conduit from the exposed ceiling.
RESIDENCE
HALL LOBBY EXPANSION:
The enclosure contractor installed insulation for the lower spandrel glass on the Perdido Street side.
The interior contractor completed painting the fur down for the lobby and mezzanine level and continued installing sheetrock on the back lobby of Bolivar and Perdido corner.