Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, March 11, 2009

 

1542 TULANE AVE.:

  • The general contractor continued patching and taping the walls in Rooms 109H, 111 and 111A.
    • They completed installing the new suspended ceiling grid in Room 109H.
    • The demolition in Room 341, 342 and 343 is proceeding.
  • The mechanical contractor continued installing new fan coil units on the 3rd Floor.
  • The painting contractor continued painting offices on the 3rd Floor and the center stairwell between the 1st and the 4th Floors.
  • The glass contractor installed the new storefront in the 1st Floor lounge and continued trim work.
  • Facility Services continued making repairs on the 1st, 2nd and 3rd Floors, painting hallways on the 3rd Floor, and connecting electrical service for fan coil units on the 3rd floor.
    • They began installing the new ceiling grid in Room 319C.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:    

  • The electrical contractor pulled control wire from the roof mounted emergency generator to the 2nd Floor.
    • They continued installing light fixtures in the 6th Floor computer lounge.
  • The contractor continued removing shaft walls from around the freight elevator.
    • The installation of the glass on the exterior stairwell has been completed.  Crews have begun caulking the glass panels.
    • Workers continued installing granite on the exterior of the new stairwell.
    • Ceiling tile was installed in the 6th Floor elevator lobby.
    • Crews continued installing the wall by the roll down fire door on the 6th Floor.
    • They have started installing sheet vinyl in the simulation labs.
    • The granite floors on the 1st Floor, Bolivar Street side are being stripped.
  • The mechanical contractor mounted actuators on the 1st and 6th Floors in the mechanical rooms on the S. Prieur Street side.
    • They capped the fuel lines on the roof and on the 1st Floor.
  • The sprinkler subcontractor continued installing sprinkler heads on the 6th Floor in the computer lounge.

 

LIBRARY COMMONS:

  • The contractor continued to paint the composite wall panels in the large multimedia room and installed sheetrock inside the Library.
  • Additional work was done on the new display case in the elevator lobby.
  • Facility Services continued installing light switches.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor continued installing the new light fixtures.

 

MEB MDL #6 RENOVATIONS:

  • The contractor installed countertops, chase covers, and casework panels.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The contractor installed additional ceiling grid in the administrative area.
  • They installed exhaust ductwork between the administrative area and the exhaust chase. 

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The contractor continued installing air conditioning plenum boxes and linear diffusers.
  • Ceiling grid was installed in the back lobby area in the C Tower.
  • The contractor began running fire alarm wires.

 

DENTAL 6th & 8th FLOOR LAB RENOVATIONS

  • The cabinet installers installed the wall-mounted and peninsula shelving in Suite 8405 .
  • The network wiring crew installed the network wiring for the peninsulas in 8405A and 8405B. 
    • They installed the network drops and wall plates for Rooms 6333 and 6335.
  • The plumbing contractor installed the gas and vacuum connections for the peninsulas in Rooms 8405A and 8405B.

 

DENTAL SCHOOL AUDITORIUM A & B RENOVATIONS

  • The contractor primed and painted the wing walls in Auditoriums A & B.

 

DENTAL SCHOOL BOILER INSTALATION

  • The contractor installed the gas piping and valves for the boiler.   
  • They assembled and prepped the boiler connections for the scheduled system tie-in.