Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, March 12, 2009

 

1542 TULANE AVE. :

  • The general contractor continued patching and taping the walls in Rooms 109H, 111 and 111A, and started installing the new suspended ceiling grid in Rooms 111 and 111A.
  • The electrical contractor began the electrical rough-in in the 1st Floor lounge.
  • The glass contractor continued installing the trim on the new storefront in the 1st Floor lounge.
  • The mechanical contractor continued installing new fan coil units on the 3rd Floor.
  • The painting contractor started patching offices on the 2nd Floor.
    • They completed painting the center stairwell between the 1st and the 4th Floors.
  • LSUHSC Facility Services continued making repairs on the 1st, 2nd and 3rd Floors and connecting electrical service for fan coil units on the 3rd Floor.
    • They completed installing the new ceiling grid in Room 319C.

 

EXTERIOR/LANDSCAPING:

  • LSUHSC Facility Services completed planting shrubs and mulching in the rear of the Resource Center along Gravier St .

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:

  • The electrical contractor installed the annunciator panels on the 1st and 2nd Floors.
    • They pulled feeder wires from the fire pump motor and jockey pump to the fire pump controller on the 2nd Floor.
    • Crews continue to pull control wire from the roof top generator to the ATS and install light fixtures in the 6th Floor computer lounge.
  • The contractor prepped the freight elevator for the new flood wall.
    • A crew began installing cabinets for the reception desk on the 6th Floor.
    • Others began installing ceramic border tile in the 6th Floor computer lounge.
    • They continue installing exterior granite on the new stairwell and caulking the glass panels.
    • Additional ceiling tile was installed on the 6th Floor.
    • The sheet vinyl for the floors in the simulation labs is being laid.
    • A crew began installing VCT in the hallway.
    • They continued stripping the granite floors on the 1st Floor, Bolivar Street side.
  • The mechanical contractor removed the acid waste line above the new switchgear.
    • They continued installing supply and return grilles in the 6th Floor computer lounge.
  • The sprinkler subcontractor continued installing sprinkler heads in the 6th Floor computer lounge.

 

LIBRARY COMMONS:

  • The contractor continued to paint the composite wall panels in the large multimedia room and installing sheetrock in the library. 
  • The contractor installed glass in the display case in the elevator lobby. 
  • Facility Services installed a transfer switch for emergency lighting and installed drains for the coffee kiosk.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor continued installing light fixtures.
  • LSUHSC Facility Services re-routed pneumatic lines so they will not be in the open ceiling area.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The contractor installed additional ceiling grid in the administrative area.
  • The contractor installed new exhaust ductwork in the corridor. 

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The contractor began framing the fur down in back lobby area in Tower A.
  • Crews continued installing ceiling grid in the back lobby area in Tower C.
  • Additional fire alarm wires were run between the A & B tower lobby areas.
  • The enclosure contractor installed the single sliding door on the Bolivar St. /Perdido St. side.

 

DENTAL 6th & 8th FLOOR LAB RENOVATIONS:

  • The contractor installed the remaining base cabinets for the peninsulas in Suite 8405A .
  • The network wiring crew installed the network wiring in Rooms 8405C, 8405D, 8405E, 8405F, and 8405G and tested the network drops for Rooms 6333 and 6335.
  • The plumbing contractor installed sink connections (hot water, cold water, and drain) for the sinks in Rooms 8405C, 8405D, and 8405E.

 

DENTAL BOILER INSTALLATION:

  • The contractor completed the connection of the new boiler and insulated the steam line.