Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, MARCH 16, 2009

 

1542 TULANE AVE. :

  • The general contractor continued drywall and ceiling work in Rooms 109H, 111 and 111A, and continued installation of door jambs in 111B.
  • The electrical contractor continued electrical rough-in in the 1st Floor lounge.
  • The glass contractor installed the new glass wall leading from the lobby into the 1st Floor lounge and continued trim work on this wall and the new storefront.
  • The mechanical contractor continued installing new fan coil units on the 3rd Floor.
  • The painting contractor continued patching walls in offices on the 2nd Floor.
  • Facility Services continued making repairs on the 1st and 3rd Floors and installing thermostats for fan coil units on the 3rd Floor.

 

EXTERIOR/LANDSCAPING

  • Facility Services installed sod in the back of the Resource Center building.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION: 

  • The contractor continued prepping the freight elevator for the flood proofing.
    • Crews installed kitchen and mail room cabinets on the 6th Floor.
    • Workers continued installing exterior granite on the new stairwell.
    • Carpet was installed on the S. Prieur St. side of the 6th Floor.
    • Additional floor tile was installed in the 6th Floor computer lounge
    • Ceiling tile was installed on the 6th Floor Bolivar/Gravier Street side.
  • The mechanical contractor soldered the pipes for the medical air/gas/vacuum ceiling boxes in the simulation rooms.
  • The sprinkler subcontractor continued installing sprinkler heads in the 6th Floor computer lounge. 
  • The electrical contractor installed control wire for the new generator.
    • They wired the fire pump controller to the motor and ran conduit from the jockey pump to panel AC2A.
    • Workers installed light fixtures in the 6th Floor computer lounge area.

 

LIBRARY COMMONS:

  • The contractor installed half of the ceiling baffles and one fire extinguisher cabinet.
  • The contractor continued constructing the display case in the elevator lobby.
  • Facilities Services personnel plumbed and wired coffee kiosk equipment.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor continued installing light fixtures.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The contractor continued installing exhaust ductwork in the corridor. 
  • They modified sprinkler heads in the lab area.

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The contractor continued framing the fur down in the back lobby area in Tower A.

 

DENTAL 6th & 8th FLOOR LAB RENOVATIONS:

  • The cabinet installers installed the remaining counter tops for the peninsulas in suite 8405A and 8405B.
    • They installed the backsplash for the peninsulas in Suites 8405A and 8405B.
  • The network wiring crew installed the network wiring in Rooms 8405H, 8405I, and 8405J. 
  • The plumbing contractor installed sink connections in Rooms 8405A and 8405B and connected the fume hood in 6335.
  • The electrical contractor installed receptacles for the peninsulas in Suites 8405A and 8405B.

 

DENTAL BOILER INSTALLATION:

  • The contractor installed relief valves for the new boiler.