The general contractor continued drywall and ceiling work in Rooms 109H, 111 and 111A, and continued installation of door jambs in 111B.
The electrical contractor continued electrical rough-in in the 1st Floor lounge.
The glass contractor installed the new glass wall leading from the lobby into the 1st Floor lounge and continued trim work on this wall and the new storefront.
The mechanical contractor continued installing new fan coil units on the 3rd Floor.
The painting contractor continued patching walls in offices on the 2nd Floor.
Facility Services continued making repairs on the 1st and 3rd Floors and installing thermostats for fan coil units on the 3rd Floor.
EXTERIOR/LANDSCAPING
Facility Services installed sod in the back of the Resource Center building.
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The contractor continued prepping the freight elevator for the flood proofing.
Crews installed kitchen and mail room cabinets on the 6th Floor.
Workers continued installing exterior granite on the new stairwell.
Carpet was installed on the S. Prieur St. side of the 6th Floor.
Additional floor tile was installed in the 6th Floor computer lounge
Ceiling tile was installed on the 6th Floor Bolivar/Gravier Street side.
The mechanical contractor soldered the pipes for the medical air/gas/vacuum ceiling boxes in the simulation rooms.
The sprinkler subcontractor continued installing sprinkler heads in the 6th Floor computer lounge.
The electrical contractor installed control wire for the new generator.
They wired the fire pump controller to the motor and ran conduit from the jockey pump to panel AC2A.
Workers installed light fixtures in the 6th Floor computer lounge area.
LIBRARY
COMMONS:
The contractor installed half of the ceiling baffles and one fire extinguisher cabinet.
The contractor continued constructing the display case in the elevator lobby.
Facilities Services personnel plumbed and wired coffee kiosk equipment.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor continued installing light fixtures.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The contractor continued installing exhaust ductwork in the corridor.
They modified sprinkler heads in the lab area.
RESIDENCE
HALL LOBBY EXPANSION:
The contractor continued framing the fur down in the back lobby area in Tower A.
DENTAL
6th & 8th FLOOR LAB RENOVATIONS:
The cabinet installers installed the remaining counter tops for the peninsulas in suite 8405A and 8405B.
They installed the backsplash for the peninsulas in Suites 8405A and 8405B.
The network wiring crew installed the network wiring in Rooms 8405H, 8405I, and 8405J.
The plumbing contractor installed sink connections in Rooms 8405A and 8405B and connected the fume hood in 6335.
The electrical contractor installed receptacles for the peninsulas in Suites 8405A and 8405B.
DENTAL
BOILER INSTALLATION:
The contractor installed relief valves for the new boiler.