Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, March 5, 2009

 

1542 TULANE AVE. :

  • The general contractor continued painting in offices on the 3rd Floor and began painting in Room 109H. 
  • The mechanical contractor continued installing new fan coil units on the 3rd Floor.  
  • The painting contractor continued painting offices on the 3rd Floor. 
  • Facility Services continued making repairs on the 1st and 3rd Floors, painting hallways on the 3rd Floor, and connecting electrical service for the new fan coil units.

 

EXTERIOR/LANDSCAPING:

  • LSUHSC Facility Services planted shrubs in the rear of the Resource Center .

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION: 

  • The contractor installed ceiling tile on the Gravier St. side of the 6th Floor.
    • A crew continued installing the wall around the new roll up fire door on the 6th Floor/
    • Another crew is installing CMU walls on the Bolivar St. side of the 1st Floor.
    • The exterior glass is being installed on the exterior of the new stairwell. 
  • The mechanical contractor continued installing the diesel fuel pipes on the 1st Floor,  CSRB side.
    • They continue to install the supply and return grilles on the Gravier St. side of the 6th Floor.
  • The electrical contractor installed wires from the disconnects to the roof mounted emergency generator.
    • They ran conduit to the battery charger and the heater for the generator on the roof.
    • Electricians installed exit signs, strobes and speakers on the CSRB side of the 6th Floor.
    • They installed the VFD on the 6th Floor in the Bolivar St. side mechanical room and tied in the fire phones on the 6th Floor.  
  • The sprinkler contractor installed sprinkler heads on the 6th Floor, Gravier St. side.
  • AT&T began pulling the main telephone feeder cable.

 

LIBRARY COMMONS:

  • The contractor installed window shades. 
  • They continued to paint the composite wall panels in the small multimedia room and began installing the wooden ceiling trim in the study area.
  • The contractor continued installing the display case in the elevator lobby and near the stairs.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor began installing granite on the columns.
  • They installed the door frames on the north side of the lobby.

 

MEB MDL 6 RENOVATIONS:

  • The A/V contractor completed programming and testing the new audio/video components. 
  • The contractor connected drains to the eight sinks.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The contractor is painting walls in the administrative area.

 

RESIDENCE HALL LOBBY EXPANSION: 

  • The contractor laid the final mortar bed layer in the two corner lobby areas. 
  • The enclosure contractor installed break metal on the underside of the roof above the entrance door. 
  • The interior contractor continued framing and installing sheetrock for the fur down in the expanded lobby area.

 

DENTAL SCHOOL A and B AUDITORIUM RENOVATIONS

  • The contractor taped and floated the new (smaller) wing walls in both auditoriums.

 

DENTAL 6th & 8th FLOOR LAB RENOVATIONS:

  • The contractor installed base cabinets and shelving in the large rooms on the 8th Floor.

 

ALLIED HEALTH/ NURSING ROOF REPLACEMENT

  • Work has begun on the project.  The contractor is removing the old ballast (gravel) from the roof.