The general contractor completed painting the walls in Rooms 341, 342 and 343.
Workers began installing the ceiling grid in the three offices.
Another crew continued finishing the drywall in the 1st Floor lounge.
LSUHSC Facility Services continued completing electrical repairs on the 1st and 2nd Floors.
They installed door locks on Rooms 111 and 111A and continued painting on the 3rd floor.
EXTERIOR/LANDSCAPING:
Facility Services continued installing irrigation piping at the corner of Perdido St. and S. Roman St .
LIONS/LSU
CLINIC PERMANENT REPAIRS AND MITIGATION:
The contractor installed base molding near the 6th Floor reception desk and in the hallway between the simulation rooms.
They continue to install glass in the stairwell.
Workers installed sprinkler heads in the 6th Floor computer lounge.
Floor tile was laid on the Bolivar St. side of the 1st Floor.
They installed wall tile on the 1st Floor, Bolivar Street side.
A crew continues installing granite pavers around the new stairwell.
The electrical contractor finished trimming out and testing the fire alarm devices on the 6th Floor.
Electricians continued installing lights in the 1st Floor restrooms.
LIBRARY
COMMONS:
The contractor hung wallpaper beneath the windows.
MEB
PHARMACOLOGY LAB RENOVATIONS:
The casework contractor installed the second side of the peninsula casework in Room 5219.
Workers installed casework and countertops in Rooms 512A and 5124.
They hung shelves in Room 5124 and installed sinks in Rooms 5219A, 5262.
The final coat of paint was applied to Rooms 5262B, 5264, 5262A, and 5206C
ALLIED
HEALTH/NURSING RE-ROOFING PROJECT:
The contractor removed a 30 ft. by 30 ft. section of the roof at the corner of Roman St. and Gravier St .
The contractor applied the two-ply roofing system to the same section.
RESIDENCE
HALL LOBBY EXPANSION:
The interior contractor sanded and prepped the fur down in the expanded lobby area.
The interior contractor installed ceiling tiles in the A Tower lobby.
DENTAL SCHOOL
AUDITORIUMS A & B RENOVATIONS:
The electrical contractor installed junction boxes for conduit in the crosswalk (the conduit stretches between the Auditoriums and the rack room; Room 4202B).