1542 TULANE AVE. :

  • The general contractor continued finishing drywall in the 1st Floor lounge.
    • They applied the first coat of paint in the auditorium.
  • The ceiling grid contractor continued repairing the 3rd Floor hallway ceiling grid.
    • Workers began making repairs to the 2nd Floor front hallway ceiling.
  • The cleaning contractor continued cleaning offices along the center hallway on the 3rd Floor. 
  • Facility Services continued making various electrical repairs on the 1st and 3rd Floors and painting rooms on the 2nd and 3rd Floor.

 

EXTERIOR/LANDSCAPING:

  • Facility Services finished installing new sod at the corner of S. Roman St. and Perdido St .

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:   

  • The contractor applied the 2nd coat of epoxy on the floors of the 1st Floor mechanical rooms.
    • Crews continued framing and sheet rocking the shaft walls of the stairwell on the 3rd and 4th levels.
    • They finished grouting the granite pavers outside of the stairwell.
    • Workers waterproofed the granite wall panels on the new stairwell.
    • The contractor continued the installation of CMU walls in the telephone room.
  • The electrical contractor installed a junction box for the new fiber cables on the 6th Floor Bolivar Street side.
    • They piped in the sump pumps for the elevators.
    • Electricians wired the firemans switch for the exhaust fans in the new stairwell and installed door closure on the 6th Floor, Gravier Street side.
  • Stryker installed microphones in the large lecture room on the 6th Floor.

 

LIBRARY COMMONS:

  • The contractor finished installing the restroom partitions.
  • The ceiling in the elevator lobby was repaired.
  • LSUHSC electricians trimmed out the electrical receptacles.

 

MDL-3 RENOVATIONS:

  • The contractor removed the existing partitions from the main MDL room and removed the casework and ceiling from Room 4108A.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor taped and floated the fur down across from the elevators.
  • The wall panel contractor continued installing wall panels along the Medical Center Stores wall.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The contractor installed receptacle raceways above the laboratory furniture. 
  • Workers connected drains to the sinks in the laboratory furniture. 

 

ALLIED HEALTH/NURSING RE-ROOFING PROJECT:

  • The contractor installed insulation and a cap forty feet beyond the elevator penthouse toward South Roman Street .  

 

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The electrical contractor installed additional conduit and junction boxes in the crosswalk outside Room 4202.

 

COX CABLE INSTALLATION:

  • The contractor installed cable lines from the 1st Floor to the 9th Floor in the Lions/LSU Clinic Building.