The general contractor continued finishing drywall in the 1st Floor lounge.
Crews continued installing ceiling grid in the 1st Floor lounge.
They finished painting the auditorium.
The ceiling grid contractor continued repairing the 2nd Floor front hallway ceiling.
The cleaning contractor continued cleaning offices on the 3rd Floor.
Duplicating and Printing was relocated from their temporary location in the Residence Hall to Rooms 110, 111 and 111A.
Facility Services continued making electrical repairs on the 1st and 3rd Floors and painting rooms on the 2nd and 3rd Floors.
LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:
The contractor installed new sprinkler lines in the landscaping at the front of the building; replacing lines that were removed during the excavation for the new exterior stairwell.
They began installing the extension of the metal platform on the roof for the electrical panel.
Workers installed carpet on the Gravier St. side of the 6th Floor.
They continue installing trim for the windows of the stair tower at the 4th and 5th levels.
Crews are installing the shaft walls of the stairwell at the 2nd and 3rd levels.
The new shaft walls on the 4th through the 6th levels are being taped and floated.
Workers continued to waterproof the granite wall panels on the new stairwell.
The electrical contractor began terminating the new fiber cables in the 6th Floor network closet.
They ran wire for the sump pumps in the elevator pits.
Door closures were installed on the Bolivar St. side of the 6th Floor.
LIBRARY COMMONS:
The contractor patched the opening in the ceiling of the elevator lobby.
MDL-3 RENOVATIONS:
The contractor abated the floor in the room.
RESIDENCE HALL LOBBY EXPANSION:
The contractor completed installing ceiling grid for the sheetrock ceiling underneath the mezzanine level of the A & B Towers and in the expanded lobby area.
The contractor continued installing ceiling grid for the acoustical ceiling between the B & C Towers.
The contractor cored holes for floor boxes between the A & B Towers .
MEB 2ND FLOOR LOBBY RENOVATIONS:
The contractor installed surface mount lights on the Bolivar Street side of the lobby.
They taped and floated the walls around the new doors across from the elevators.
MEB PHARMACOLOGY LAB RENOVATIONS:
The contractor continued installing receptacle raceways and light fixtures in the laboratory area.
ALLIED HEALTH/NURSING RE-ROOFING PROJECT:
The contractor removed the remaining portions of the old roof and installed the temporary cap over those areas of the roof.
This phase of the work is complete on the roof of the building.
The contractor removed approximately three quarters of the old roof from the walkway roof and started installing insulation and the cap sheet.
DENTAL SCHOOL AUDITORIUMS A
& B RENOVATIONS:
The contractor installed sheetrock and floor tile in Room 4202B.