Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, MAY 14, 2009

 

NOTICE:  On Thursday, May 14th, from 6:00 PM until midnight, there will be a chilled water outage at the Clinical Education Building .  During this time there will be no air conditioning in the building.  This work is needed to repair leaks.

 

NOTICE:  On Friday, May 15th, from 6:00 PM to 3:00 AM, there will be a steam outage at the Dental School Clinic Building .  This outage is needed so that old steam condensate lines can be capped.  During this outage, there will be no steam available for the autoclaves in the Clinic Building .

 

1542 TULANE AVE. :

  • The contractor applied the second coat of paint on the walls in the 1st Floor lounge. 
  • Crews wired additional fan coils in 3rd Floor offices along Tulane Ave.
  • The sprinkler contractor worked on the dry pipe system. 
  • The contractor installed pedestrian rails. 
  • Facility Services continued making electrical repairs and painting on the 2nd and 3rd Floors.

 

LIONS/LSU CLINIC BLDG PERMANENT REPAIRS AND MITIGATION:    

  • The electrical contractor installed floor boxes in the 6th Floor simulation rooms.
    • They tested phone cables on the 6th Floor and finished installing LED lights in the 6th Floor computer lounge and at the reception desk.
  • The contractor cut the tile in the 6th Floor computer lounge area to accommodate the new floor box covers.  

 

LIBRARY COMMONS:

  • The contractor continued installing door hardware.

 

RESIDENCE HALL LOBBY EXPANSION:

  • The contractor taped and floated the walls of the network closet.
  • They installed ceiling tiles between the B Tower and the C Tower.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor installed wooden panels near the Womens restroom.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The network wiring contractor continued pulling network wires in the lab area. 
  • The contractor continued to install wire molding in the lab area.

 

ALLIED HEALTH/NURSING BLDG  RE-ROOFING PROJECT:

  • The contractor continued replacing the parapet wall cap along the MEB loading dock side of the roof.  The crew is working towards Gravier Street . 

     

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The contractor installed the remaining ceiling tiles in Auditorium B.
  • The electrical contractor wired the breakers in the new sub-panels and pulled wires from the new electrical sub-panels to the lighting distribution panels.
  • The flooring contractor installed carpet on the lower level in Auditorium A.