Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, MAY 20, 2009

 

1542 TULANE AVE. :

  • The telephone company activated phone lines on the 3rd and 4th Floors and LSUHSC Computer Services is checking the phone lines.
  • The contractor taped and floated the new wall in the 1st Floor lobby area that leads to the basement. 
  • The contractor installed the carpet for the 2nd Floor lounge. 
  • Facility Services personnel continued painting on 3rd and 4th floors.

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued planting and mulching around the MEB at the corner of Perdido and S.  Roman Streets.

 

LIONS/LSU CLINIC PERMANENT REPAIRS AND MITIGATION:    

  • The mechanical contractor continued installing the 1st Floor Bolivar Street restroom fixtures. 
  • The contractor built the 1st Floor knee walls in the exterior stairwell.

 

RESIDENCE HALL LOBBY EXPANSION:

  • The floor contractor continued installing tiles on the Perdido Street side of the lobby.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • The contractor installed a new weather-tight NEMA-4 enclosure for the RTU #1 control panel. 

 

MEB MDL 3 RENOVATIONS:

  • The contractor continued installing steel track for the new partition in Room 4108A.
  • They continued framing stud around the steel track for sound insulation.
  • The contractor continued stubbing up plumbing for the new casework.

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor continued installing wooden wall panels near the elevators.

 

MEB PHARMACOLOGY LAB RENOVATIONS:

  • The network wiring contractor continued pulling network wires in the lab area. 
  • The contractor continued installing the exhaust ductwork.

 

ALLIED HEALTH/NURSING BLDG RE-ROOFING PROJECT:

  • The contractor continued replacing the parapet wall cap along South Roman Street .   

     

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The contractor installed the acoustical wall panel frames on the Campus Road side of Auditorium A.
  • The electrical contractor wired and energized the new lighting and power panels for both auditoriums.      
  • The contractor pulled wires for the new emergency panel X4RC. 
  • The A/V contractor pulled additional wires from the auditoriums to Room 4208 (outside of the new rack room 4202B).