The contractor prepped the floor in Room 122F (Womens restroom) to receive new VCT.
The contractor prepped Rooms 203 and 203A for mastic and insulation removal.
DENTAL SCHOOL
AUDITORIUM A & B RENOVATIONS:
The A/V contractor installed and configured additional components for the podium in Auditorium B; podium 95% complete.
A new projector was installed in Auditorium B.
The broken window glass on the 4th Floor crosswalk was replaced.
EXTERIOR/LANDSCAPING:
Facility Services continued installing irrigation piping on the Gravier Street side of the Roman Garage.
MEB
AIR HANDLING UNIT REPLACEMENT:
Facility Services completed shifting the temporary A/C units to the 4th and 5th Floor Quadrant D (corner of Bolivar Street and Perdido Street ) and monitored performance.
The contractor demolished the old air handling units 4-D and 5-D.
They installed new ductwork and installed new AHUs 4-D and 5-D.
Crews continued installing piping.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor completed installing the electrical door hardware.
The contractor installed a register above the digital sign.
MEB
7th FLOOR PHYSIOLOGY LABS RENOVATIONS:
The contractor completed roughing in the electrical for Rooms 7241 and 7250.
Workers laid VCT tiles in Rooms 7221, 7241, and 7250.
Crews patched, taped and floated walls in Rooms 7221, 7241, and 7250
ALLIED
HEALTH/NURSING BLDG. REROOFING PROJECT:
The contractor continued trimming the main entrance canopy roof and the 4th Floor roof near the S. Roman Street side.