Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, AUGUST 5, 2009

 

1542 TULANE AVE. :

  • The contractor primed the 1st Floor bathrooms behind the coffee kiosk and installed sheetrock on the rear wall of the kiosk area. 
  • The plumbing contractor completed roughing in the kiosk.  

 

ALLIED HEALTH/NURSING BLDG. ROOF REPLACEMENT:

  • The contractor core-drilled the corner penetrations. 

 

DENTAL SCHOOL AUDITORIUMS A & B RENOVATIONS:

  • The electrical contractor terminated additional network wires for Auditorium A.
  • The A/V contractor continued programming the lighting and control panel for the podiums.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring and adjusting the temporary A/C units in the A Quadrant (corner of South Roman Street and the MEB loading dock).
  • The contractor completed installation of the duct connections between the hot and cold deck for air handling units 6-A and 7-A. 
  • Workers completed the chilled water piping at AHU 6-A and continue piping chilled water to AHU 7A. 
  • The condensate drain for AHU 7A is complete and the contractor continues piping condensate drains at 6A. 
  • Electrical wiring and control wiring installations have begun on both AHU 6A and 7A.
  • Testing and balancing of AHU 6-B and 7-B continues.

 

LANDSCAPING:

  • Facility Services continued laying sod on the Tulane Avenue side of the Roman Street Garage. 
    • This work was delayed while a large section of defective 2” irrigation piping was removed and new pipe reinstalled.

 

MEB 7TH FLOOR PHYSIOLOGY LABS RENOVATIONS:

  • The contractor installed sheetrock to close up the blocking in Room 7221.
  • Crews installed stud channel for the soffit ceiling in Room 7250.

 

RESIDENCE HALL 2nd FLOOR LOBBY RENOVATIONS:  

  • The network contractor continued running network wires.
  • The contractor installed supply air HVAC grilles and installed carpet in the recreation room.
  • The contractor began painting in the mezzanine area between the B & C Towers .