Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, OCTOBER 12, 2009

 

1542 TULANE AVE. :

  • The contractor touched-up the paint in Room 242B.
  • Workers taped and floated the sheetrock along the Tulane Avenue wall.
  • The contractor touched-up the paint on the new door in the 1st Floor lounge.

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued installing the irrigation piping at the corner of Bolivar Street and Gravier Street .
  • Crews applied new pavement markings to the Faculty parking lot at the City Park Campus.

 

LIONS/LSU CLINIC BLDG. 8TH FLOOR RENOVATION:

  • Facilities Services continued the demolition of the conference and lobby areas.
  • The Liebert unit was delivered. 

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring temporary A/C units in the 4th and 5th Floor Quadrant B (corner of South Roman Street and Perdido Street ).
  • The contractor completed insulating the chilled water piping for AHU 5-B and the hot water piping AHU 4-B.
  • They continue with electrical and controls installation.   

 

MEB 4TH FLOOR MDL #4 RENOVATIONS:

  • The contractor removed ceiling grid, tiles and existing light fixtures.

 

MEB 7th FLOOR PHYSIOLOGY LABS RENOVATIONS:

  • The contractor installed mini blinds in Room 7241 and 7250.
  • The contractor cleaned up and began working on punch list items.

 

RESIDENCE 2ND FLOOR LOBBY RENOVATIONS:

  • The contractor continued installing the front side precast panel starting from the Bolivar street side.

 

UPTOWN CHILLER REPLACEMENT:

  • Contractor pulled and terminated the wires for the chilled water pumps and their variable speed drives, condenser water pumps, chillers, and air conditioners.