Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, OCTOBER 13, 2009

 

1542 TULANE AVE. :

  • The contractor continued to float the sheetrock in the auditorium.
  • Carpet was installed in Room 242B.

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued installing the irrigation piping at the corner of Bolivar Street and Gravier Street .

 

LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • Facilities Services continued the demolition of the conference and lobby areas.
  • The contractor started making final connections to the new Liebert unit.   

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring temporary A/C units in the 4th and 5th Floors Quadrant B (corner of South Roman Street and Perdido Street ).
  • The contractor completed `insulation of the hot water piping serving AHU 5-B and continued the electrical and controls installation.   

 

MEB 4TH FLOOR MDL #4 RENOVATIONS:

  • The contractor continued removing the old ceiling grid, tiles and light fixtures.

 

MEB 7th FLOOR PHYSIOLOGY LABS RENOVATIONS:

  • The contractor installed receptacle covers and touched up paint in all four rooms.

 

RESIDENCE 2ND FLOOR LOBBY RENOVATIONS:

  • The contractor installed the light fixture in the network closet.
  • Facility Services painted the steel pole by the precast concrete bench.

 

UPTOWN CAMPUS:

  • The contractor started cleaning the chilled water loop piping in preparation for connection to the main hospital building. 
  • Tonight’s outage was cancelled because contractor was not prepared to install new breakers.