Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, OCTOBER 15, 2009

 

1542 TULANE AVE. :

  • The contractor installed temporary lighting for the 1st Floor Garage Entrance.
  • They demolished the ceramic block wall between Rooms 203 and 204.

 

DENTAL SCHOOL FENCE REPLACEMENT:

  • The contractor anchored 50 new fence posts in concrete along Florida Ave.  
  • Crews set the gate posts for the new chain-link fencing along Florida Avenue .

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued irrigation piping along the Bolivar Street side of the Roman St. Garage.

 

LIONS/LSU CLINIC 8TH FLOOR RENOVATIONS:

  • Facilities Services completed the demolition of the conference and lobby areas.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring temporary A/C units in the 4th and 5th Floors Quadrant B (corner of South Roman Street and Perdido Street ).
  • The contractor completed the electrical and controls installation for AHUs 4-B and 5-B and began testing and balancing the new units.   

 

MEB 4TH FLOOR MDL #4 RENOVATIONS:

  • The contractor continued raising the steel beam that supports the partition track.

 

MEB 7th FLOOR PHYSIOLOGY LABS RENOVATIONS:

  • The contractor relocated a/c diffusers and lights in Room 7129.

 

RESIDENCE 2ND FLOOR LOBBY RENOVATIONS:

  • The contractor continued installing the top precast concrete panels on the South Roman Street side.
  • Workers installed two sets of door hardware.

 

UPTOWN CAMPUS:

  • The contractor began connecting the chilled water piping to the main hospital building.