The contractor prepped the handicap accessible ramp for handrails at the 1st Floor Garage Entrance.
CITY
PARK CAMPUS:
The contractor started installation of the top fence rail along Florida Ave.
EXTERIOR/LANDSCAPING:
Facility Services planted additional shrubs adjacent to the Roman Garage along Bolivar Street .
LIONS/LSU
CLINIC BLDG. 8TH FLOOR RENOVATIONS:
Facilities Services started roughing in the plumbing for the small coffee room.
MEB
2nd FLOOR LOBBY RENOVATIONS:
The contractor began installing replacement wall panel seals.
MEB
AIR HANDLING UNIT REPLACEMENT:
Facility Services commenced installing temporary A/C units in the 4th and 5th Floors Quadrant A (corner of South Roman Street and the MEB loading dock).
The contractor continued balancing and testing AHUs 4-B and 5-B.
MEB
4TH FLOOR MDL #4 RENOVATIONS:
The contractor roughed in for the new plumbing and electrical.
The contractor removed an existing door and removed additional bricks for the partition storage door to Room 4112A.
RESIDENCE
HALL 2ND FLOOR LOBBY RENOVATIONS:
The contractor installed sprinkler escutcheons underneath both sides of the mezzanine.
The contractor continued installing new door hardware.
RESOURCE CENTER ROOFING PROJECT:
The contractor completed the lightweight concrete installation.
UPTOWN
CAMPUS:
The contractor installed the breakers for the new chillers during the Oct 17th planned outage.
The contractor completed the chill water piping and began testing and programming the chillers.