Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, OCTOBER 21, 2009

 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • Bids for the permanent repair and mitigation project at the Resource Center were opened this afternoon by the Office of Facility Planning and Control. 
  • The bids are being evaluated and an award recommendation is expected shortly.

 

1542 TULANE AVE. :

  • The contractor cored the 2-inch stage penetration for the podium connections.
  • The contractor installed chilled water piping for the HVAC at the 2nd level garage corridor.

 

CITY PARK CAMPUS:

  • The contractor installed chain link fabric along Florida Avenue and constructed wood forms for the precast columns.

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued installing irrigation piping adjacent to the Roman Garage along S. Roman Street .

 

LIONS/LSU CLINIC BLDG. 8TH FLOOR RENOVATIONS:

  • The general contractor started laying out the curved wall for the conference room. 

 

RESOURCE CENTER LIBRARY RENOVATIONS:

  • The contractor fixed the floor tile and carpet at the main entrance. 

 

MEB 2nd FLOOR LOBBY RENOVATIONS:

  • The contractor completed installing the metal wall panels.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued installing temporary A/C units in the 4th and 5th Floors A Quadrant (corner of South Roman Street and the MEB loading dock).
  • The contractor continued balancing and testing AHUs 4-B and 5-B.   

 

MEB 4TH FLOOR MDL #4 RENOVATIONS:

  • The contractor continued roughing in the new electrical.
  • The contractor continued installing sheetrock in Room 4210.

 

RESIDENCE HALL 2ND FLOOR LOBBY RENOVATIONS:

  • The contractor finished installing all of the precast panels.
  • The contractor continued installing door hardware.

 

RESOURCE CENTER ROOFING PROJECT:

  • The contractor started the installation of the first ply of the 2-ply roofing on the corner of Gravier St and Bolivar St .  

 

UPTOWN CAMPUS:

  • The contractor is painting and insulating chill water piping at the tie-in points. 
  • The new chiller is providing chill water to the main hospital. 
  • The temporary chiller has been turned off.