RESOURCE CENTER PERMANENT REPAIRS AND MITIGATION:

  • The architect has recommended that the contract be awarded to the low responsive bidder and LSUHSC has concurred. 
  • The award of the contract should begin shortly.

 

1542 TULANE AVE. :

  • The contractor installed the carpet and vinyl tile for the 2nd level garage corridor.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services completed installing temporary A/C units in the 4th and 5th Floors A Quadrant (corner of South Roman Street and the MEB loading dock).
  • The contractor began selective demolition of collateral equipment on AHUs 4-A and 5-A.   

 

MEB 4TH FLOOR MDL #4 RENOVATIONS:

  • The contractor continued installing new stud walls in Room 4210.

 

UPTOWN CAMPUS CHILLER REPLACEMENT:

  • The contractor cleaned up the site today.