Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, OCTOBER 6, 2009

 

1542 TULANE GARAGE ENTRANCES:

  • The contractor taped and floated the walls in Room 242 for the 2nd level garage corridor.

 

EXTERIOR/LANDSCAPING:

  • Facility Services continued installing irrigation piping adjacent to the Roman St. Garage along Bolivar Street and began the final grading around the T-lot.

 

LIONS/LSU CLINIC BLDG. 8TH FLOOR RENOVATIONS:

  • Facilities Services continued the demolition of the conference and lobby areas.
  • The general contractor hung sheetrock in Room 804 (lab area that is being converted into the conference room). 

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring temporary A/C units in the 4th and 5th Floor Quadrant B (corner of South Roman Street and Perdido Street ).
  • The contractor completed installing chilled water piping for AHU 4-B and 5-B.
  • They continued installing ductwork for both of the new air handling units.
  • Crews balanced RTU 1, RTU 2, and all AHUs on the 6th and 7th Floors.   

 

MEB 4TH FLOOR MDL #4 RENOVATIONS:

  • The contractor removed the old floor tile. 

 

MEB 7th FLOOR PHYSIOLOGY LABS RENOVATIONS:

  • The contractor buffed and waxed the floors in all 4 rooms

 

RESIDENCE HALL LOBBY RENOVATIONS:

  • The contractor continued placing and setting the precast stone on the concrete wall.

 

RESOURCE CENTER ROOFING PROJECT:

  • The contractor prepped the roof deck for the lightweight concrete on the corner of Gravier St. and S. Prieur St .).

 

UPTOWN CAMPUS CHILLER REPLACEMENT:

  • The Uptown Campus is the former site of the New Orleans Adolescent Hospital .
  • The contractor installed the condenser water pumps and completed the exterior condenser piping. 
  • The contractor removed the existing chilled water pumps.