The contractor continued installing lights in the 2nd Floor garage entryway.
CITY
PARK CAMPUS:
The contractor removed the chain link fence along the de Saix Subdivision; from Moss Street to the security camera.
MEB
AIR HANDLING UNIT REPLACEMENT:
Facility Services continued monitoring and adjusting the temporary A/C units in Quadrant A of the 4th and 5th Floors (corner of South Roman Street and the MEB loading dock).
The contractor completed installing the hot water piping for AHU 5-A.
They completed the pipe insulation for AHU 4-A.
Work continued on the ductwork for both units.
Workers started the electrical and controls installation.
RESIDENCE
HALL 2ND FLOOR LOBBY RENOVATIONS:
The contractor patched and leveled floor by the precast bench area.
RESOURCE CENTER ROOF REPLACEMENT:
The contractor replaced the second row of glass panes on the atrium roof.
The contractor applied one ply of the 2-ply roofing system at the NW corner of the roof. .
UPTOWN
CAMPUS CHILLER REPLACEMENT:
The contractor installed additional insulation on the chilled water piping.