Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, NOVEMBER 20, 2009

 

1542 TULANE AVE. :

  • The contractor installed ductwork and grilles for the 2nd Floor garage corridor.
  • The sprinkler head in Room 202A were replaced.
  • Workers prepped the ramp for the flooring finish at the 1st Floor garage entrance.

 

FENCING PROJECT:

  • The contractor completed the fence fabric installation along Castine Street .
  • Crews set the remaining fence posts along the DeSaix Subdivision. 

 

EXTERIOR/LANDSCAPING:

  • The contractor poured concrete for the new concrete curb on Bolivar St. between Poydras St. and Perdido St.

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring the temporary A/C in Quadrant D of the 2nd and 3rd Floors.
  • The contractor completed installing the hot water piping for AHU 2-D and 3-D.
  • They continue installing electrical and controls for AHU 2-D and 3-D.   

 

RESOURCE CENTER ROOF REPLACEMENT:

  • The contractor installed the cap sheet on the Tulane Ave. side or the roof.

 

LIONS/LSU CLINIC BLDG 7TH FLOOR LAB RENOVATIONS:

  • The contractor continued demolishing sheetrock and wall framing.     

 

LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • The contractor continued the electrical rough-in for the lights and receptacles in the Directors office and the small conference room.   

 

MEB MDL 4 RENOVATIONS:

  • The contractor continued installing ceiling grid in the main MDL room.
  • They installed the digital signage in the elevator lobby.

 

MEB 2ND FLOOR AUTOPSY HVAC UPGRADE:

  • The contractor installed one VAV box above the 2nd Floor ceiling.
  • Crews continued installing ductwork inside the autopsy room.