WEDNESDAY, NOVEMBER 25, 2009
MEB
AIR HANDLING UNIT REPLACEMENT:
- Facility Services continued monitoring the temporary A/C units in Quadrant D of the 2nd and 3rd Floors.
- The contractor completed the installation of the controls for AHUs 2-D and 3-D and began testing and balancing the new units.
RESOURCE CENTER ROOF REPLACEMENT:
- The contractor laid the white cap layer on all main roof drains and started installing the white cap layer on the Gravier St. side of the roof.
LIONS/LSU
CLINIC BLDG 7TH FLOOR LAB RENOVATIONS:
- The contractor continued demolition of old sheetrock and wall framing.
LIONS/LSU
CLINIC BLDG 8TH FLOOR RENOVATIONS:
- The contractor framed up the elevator lobby ceiling.
MEB
MDL 4 RENOVATIONS:
- The contractor completed patching the floor in the main MDL room.
MEB
2ND FLOOR AUTOPSY HVAC UPGRADE:
- The contractor continued installing new ductwork inside the autopsy room.
MEB
EXTERIOR SIGNAGE:
- The contractor installed the new letters “LSU HEALTH SCIENCES CENTER .â€
|