TUESDAY, NOVEMBER 3, 2009

 

1542 TULANE AVE. :

  • The contractor installed exit lights and painted the sprinkler pipe in the 2nd Floor garage entryway.   
  • The contractor installed the handrails on the handicap accessible ramp for the 1st Floor garage entrance.

 

CITY PARK CAMPUS:

  • The contractor set new fence posts along the de Saix Subdivision from Moss Street to the security camera.

 

EXTERIOR/LANDSCAPING:

  • Facility Services planted annuals at various locations around the Downtown Campus. 

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring and adjusting the temporary A/C units in Quadrant A of the 4th and 5th Floors (corner of South Roman Street and the MEB loading dock).
  • The contractor completed the pipe insulation for AHU 5-A.
  • They completed installing the ductwork for AHU 4-A and 5-A.
  • The electrical and controls installation continues.   

 

LIONS/LSU CLINIC BLDG. 8TH FLOOR RENOVATIONS:

  • The contractor completed framing the curved wall.

 

RESOURCE CENTER ROOF REPLACEMENT:

  • The contractor replaced one additional row of glass in the atrium roof. 
    • Three of fourteen rows have been completed.
  • The contractor completed applying the first ply of the 2-ply roofing system along South Prieur and underneath the Liebert units.   

   

MEB AUTOPSY HVAC EXHAUST UPGRADE:

  • The contractor continued to hang new exhaust ducts near the freight elevator.

    

MEB MDL 4 RENOVATIONS:

  • The contractor roughed in the plumbing.

 

UPTOWN CAMPUS CHILLER REPLACEMENT:

  • The contractor completed installation of the insulation on the chilled water piping.