LIONS/LSU CLINIC BLDG 8TH FLOOR RENOVATIONS:

  • The contractor installed additional conduit and electrical wire in the large conference room.
  • Facility Services started running the drain lines for the break room. 

 

LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS:

  • The contractor roughed in electrical conduit and boxes for the new lighting.
  • Crews started installing the stud bracing

  

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued monitoring the temporary A/C units in Quadrant C of the 2nd and 3rd Floors.
  • The contractor continued ductwork installation on AHU 2-B.
  • They completed piping installation on AHU 2-B.
  • Workers completed the installation of the duct work and exhaust fan in mechanical room 2-A.
  • The contractor began to test and balance the new air handling units.    

 

MEB AUTOPSY HVAC UPGRADE:

  • The contractor installed supply HVAC duct in the Womens bathroom.

 

MEB 4TH FLOOR MDL 4 RENOVATIONS:

  • The contractor continued installing new casework in the main MDL room.
  • Electricians continued connecting power to the new light fixtures.
  • Workers installed ceiling tiles in the main MDL room.

 

FENCE REPLACEMENT PROJECT:

  • The contractor installed top, bottom, and mid rails for the fence at the Castine Street and DeSaix Street entrances.