EXTERIOR/LANDSCAPING:

  • Facility Services continued irrigation piping installation and grading along Bolivar Street adjacent to the Residence Hall parking lot.

 

1542 TULANE AVE. FIRST FLOOR ADA ENTRANCE:

  • The contractor installed bollards on the 1st Floor. 

 

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services continued installation of the temporary A/C units in Quadrant C of the 2nd and 3rd Floors and removed the temporary wall in Campus Stores.
  • The contractor completed testing and balancing AHUs 2-D and 3-D.
  • They continued electrical preparations for AHUs 2-C and 3-C.  

 

LIONS/LSU CLINIC 8TH FLOOR RENOVATIONS:

  • The contractor continued hanging sheetrock on the fur down in the main entrance and around the columns in the large conference room.
  • The contractor roughed in the electrical for the small conference room and the Directors office. 

 

LIONS/LSU CLINIC 7TH FLOOR LAB RENOVATIONS:

  • The contractor continued the mechanical demolition and started installing the heating hot water lines.       

 

MEB MDL 4 RENOVATIONS:

  • The contractor installed VCT in Rooms 4215A and 4210.
  • Crews continued relocating sprinkler heads in the main MDL room.

 

MEB EXTERIOR SIGNAGE:

  • The contractor completed the wiring of the sign; the sign is fully functional.