ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued removing sheetrock and ceilings in Rooms 245 and 256.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st Floor near the front doors and removed wires from the security desk.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor taped, floated and primed the sheetrock in the large and small conference rooms and laboratory room 804.

RESIDENCE HALL LOBBY ROOF FLASHING:

  • The contractor completed installing metal flashing and installed the exterior metal panel in apartment C34.

RESIDENCE HALL FIRE ALARM UPGRADE:

  • Siemens finished connecting the flow/tamper switches for the A tower.

EXTERIOR/LANDSCAPING:

  • Facility Services completed installing the irrigation station for shrubs in the center section of the horseshoe drive.
  • They trenched and installed 95% of the station for turf on the bayou side of the drive.