MONDAY, FEBRUARY 22, 2010ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: · The contractor continued removing sheetrock and ceilings from Rooms 245 and 256. · They removed walls in the 1st Floor bathroom. · Plumbing fixtures, lights and tiles were removed from 1st Floor bathrooms near the switchgear. · The contractor installed valves on the heating hot and chill water lines.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION: · The contractor ran conduit on the 1st Floor from the new switchgear room to the new ATS room. LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS: · The contractor painted the fur down in the lobby area. · Sprinkler heads were installed in the large conference room. LIONS/LSU CLINIC 7th FLOOR RENOVATIONS: · The plumbing is being connected to the lab benches. · The contractor pulled wires for the new lighting and receptacles. RESIDENCE HALL FIRE ALARM UPGRADE: · Contractor installed fire alarm system devices in the 1st Floor fire pump room. · They began writing the programming for the new fire summary panel. FENCE REPLACEMENT PROJECT: · The contractor poured 8 of the 25 monumental columns. EXTERIOR/LANDSCAPING: · Facility Services finished removing old vegetation on the Clinic Building side of the horseshoe drive. · They started removing old vegetation from the center section. · Crews trenched for the next irrigation station on the Florida Avenue side of the Clinic Building and continued installing valve boxes. |
| Disclaimer | © 2013 LSUHSC | Privacy Policy |