ALLIED HEALTH/NURSING PERMANENT REPAIRS & MITIGATION:

·         The contractor completed removing sheetrock and studs from Stairwell 3.

·         They began running electrical lighting conduit in the Bolivar St. side of the building.

·         Crews continued removing sheetrock and metal studs from in the Tiger Room.

 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

·         The contractor removed the metal studs in the parking office area.

·         They continued installing conduit on the 1st Floor between the new switchgear location and the fire pump and between the new switchgear location and the tap box in Room 219.

 

LIONS/LSU CLINIC BLDG 7th FLOOR LAB RENOVATIONS:

·         The contractor primed the walls.

 

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

·         The contractor continued taping and floating the sheetrock in the large conference room and reception area.

·         Workers installed the ceiling grid and supply grilles in the small conference room.

 

MEB 2ND FLOOR AUTOPSY HVAC UPGRADE:

·         The contractor laid out the plumbing piping for the second morgue table.

 

RESIDENCE HALL FIRE ALARM UPGRADE

·         The contractor continued programming modules in the new fire alarm summary panel.