MONDAY, MARCH 1, 2010ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: · The contractor continued demolition in Rooms 211, 212, 233 and 236. · Crews installed electrical conduit in the main corridor of the 1st Floor. RESOURCE CENTER PERMANENT REPAIRS & MITIGATION: · On Saturday, the two electrical transformers located on the 1st Floor were raised to a height that will prevent damage from a future flood event. · The contractor installed new isolation valves for both of the restroom water risers. · Workers continue to run conduit for the new ATS room. · The plumbing lines in the 1st Floor restrooms for the toilets that are being removed were capped. · The contractor raised the water lines for the new ADA toilets in the 1st Floor restrooms. RESIDENCE HALL PERMANENT REPAIRS & MITIGATION: · The contractor delivered the wood piles to the site. LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS: · The contractor installed the window storefront between the adjacent labs. RESIDENCE HALL FIRE ALARM UPGRADE: · Crews installed smoke detectors in the elevator penthouses, installed pull stations in the stairwells and installed relay modules for the roll-up doors in the garage. · The old fire panel was removed from the 1st Floor University Police office. · The contractor continued programming the new fire alarm panel. FENCE REPLACEMENT PROJECT: · The contractor formed up 8 additional monumental columns. 24 of the 25 columns have now been formed up and/or poured. EXTERIOR/LANDSCAPING: · Facility Services completed placing and grading topsoil in the center island of the horseshoe. · They continued grading in the planting beds on the Administration Building side of the horseshoe. |
| Disclaimer | © 2013 LSUHSC | Privacy Policy |