ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

·         The contractor continued installing electrical conduit in the main corridor on the 1st Floor.

·         Demolition continued in Room 244.

 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

·         The contractor marked core locations for post tension cables in the electrical rooms on Floors 4 through 8.

·         They laid out the new concrete masonry unit (CMU) walls on the 1st Floor.   

 

LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS:

·         The contractor installed 1 of 3 storefronts adjacent to the center hallway.

 

LIONS/LSU CLINIC 8th FLOOR RENOVATIONS

·         The contractor installed the linear diffusers in the large conference room.  

·         Crews continued installing hangers for the ceiling grid in the large conference room.

 

FENCE REPLACEMENT PROJECT:

·         The contractor continued painting all 24 fence columns.