MONDAY, MARCH 15, 2010ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: · The contractor continued installing electrical conduit in the main corridor on the 1st Floor. · Workers relocated domestic hot and cold water lines around the center column on the 1st Floor and started running a 5 inch roof drain from the walkway. RESOURCE CENTER PERMANENT REPAIRS & MITIGATION: · The contractor marked core locations for post tension cables in the 2nd and 3rd Floor electrical rooms and in the new ATS and pump rooms. · They continued to lay out the walls on the 1st floor. LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS: · The contractor installed the 3 storefronts adjacent to the center hallway. · Heating hot water lines were run to the VAV boxes. LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS: · The AV contractor started running speaker wire in the large conference room. FENCE REPLACEMENT PROJECT: · The contractor continued painting the 24 monumental fence columns. EXTERIOR/LANDSCAPING: · Facility Services completed planting shrubs and mulching the island in the horseshoe. · They mulched the planting bed on the Clinic Building side of the horseshoe. · Crews continued installing irrigation piping along Florida Avenue adjacent to the Clinic Building. |
| Disclaimer | © 2013 LSUHSC | Privacy Policy |