TUESDAY, MARCH 23, 2010ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: · The contractor continued to saw cut the floor in four locations to run drain lines for the bathrooms. RESIDENCE HALL PERMANENT REPAIRS & MITIGATION: · The contractor excavated the 4th of 8 pile caps. RESOURCE CENTER PERMANENT REPAIRS & MITIGATION: · The contractor completed drilling 9 of 16 floor penetrations for the electrical riser and emergency fuel line. CEB COVERED WALKWAY: · The contractor started demolition of the old sidewalk that runs parallel to the District Entergy Garage and removed the awning connected to the Clinical Education Building. LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS: · The contractor continued to prep the sheetrock wall. LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS: · The contractor continued running conduit from the network closet to the podium in the large conference and small conference rooms. · Facility Services finished installing the 8 control valves for the VAV boxes EXTERIOR/LANDSCAPING: · Facility Services completed removing existing vegetation from the patio courtyard. · They continued trenching for irrigation piping in the courtyard. |
| Disclaimer | © 2013 LSUHSC | Privacy Policy |