WEDNESDAY, MARCH 3, 2010ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: · The demolition in Rooms 211, 212, 233 and 236 is proceeding. · The contractor continued installing electrical conduit in the 1st Floor main corridor. RESOURCE CENTER PERMANENT REPAIS & MITIGATION: · The contractor continued to run conduit for the new ATS room. · New copper water lines are being installed. RESIDENCE HALL PERMANENT REPAIRS & MITIGATION: · The contractor drove 36 of the 50 wood piles needed for the new raised structure. LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS: · The contractor started installing the frames for the storefront system adjacent to the main corridor. RESIDENCE HALL FIRE ALARM UPGRADE: · Contractor installed duct detectors for air handling unit 3 and removed inactive fire alarm wiring associated with the old fire alarm summary panel. EXTERIOR/LANDSCAPING: · Facility Services planted shrubs in the planting beds on the Clinic Building side of the horseshoe. |