Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, MARCH 5, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit in the main corridor on the 1st Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor installed new copper lines and hangers for the new domestic water lines on the 1st Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The last of the 30 piles was driven and the pile driving rig was removed.
  • The contractor excavated for the first of eight concrete pile caps

FENCE REPLACEMENT PROJECT:

  • The contractor poured the concrete for the 25th and final monumental fence column.

EXTERIOR/LANDSCAPING:

  • Facility Services completed installing plants by the Administration Building handicapped ramp.
  • They connected two irrigation stations to the controller and programmed each to run over the weekend.