Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, MARCH 8, 2010

 

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

·         The contractor continued installing electrical conduit in the main corridor on the 1st Floor.

·         Workers removed metal ductwork from mechanical room 1A.

 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

·         The contractor installed conduit on the 1st Floor between the new switchgear location and the backup power tap box in Room 219.

·         They removed ceiling grid on the Bolivar St. side of the 1st Floor.

 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

·         The contractor continued to excavate for the fourth of eight pile caps.

 

FENCE REPLACEMENT PROJECT:

·         The contractor removed forms for the final (25th) column.

 

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

·         The contractor began installing the storefront system.

 

EXTERIOR/LANDSCAPING:

·         Facility Services finished grading the center island from the flagpole to the end closest to the Administration Building.

·         They spread mulch in the section to the right of the Administration Building steps and adjusted the sprinklers.