TUESDAY, MARCH 9, 2010ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: · The contractor continued installing electrical conduit in the main corridor on the 1st Floor. · The metal ductwork was removed from mechanical room 1A. · Workers cored four holes on the 2nd Floor needed for re-routed plumbing utilities. RESOURCE CENTER PERMANENT REPAIRS & MITIGATION: · The contractor installed conduit for receptacles on the 1st Floor. · They removed 4 granite pavers in the front of the elevators and 4 granite pavers by the old security desk location. RESIDENCE HALL PERMANENT REPAIRS & MITIGATION: · The contractor erected wooden forms for the four pile caps. LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS: · The contractor pulled wire from the electrical room to the lab. LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS: · The contractor continued installing the storefront system. RESIDENCE HALL FIRE ALARM REPLACEMENT: · The contractor completed transferring all of the new devices to the new fire alarm summary panel and activated the panel. MEB MORGUE AUTOPSY ROOM HVAC UPGRADES: · The morgue passed the State Fire Marshal Inspection. MEB MDL RENOVATIONS: · All four of the renovated Multi Disciplinary Labs passed the State Fire Marshal Inspection. EXTERIOR/LANDSCAPING: · Facility Services continued grading the center island from the flagpole to Florida Avenue. |
| Disclaimer | © 2013 LSUHSC | Privacy Policy |