WEDNESDAY, APRIL 14, 2010
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continued laying CMU block in the stairwell near the MEB loading dock.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor installed forms and steel rebar to prepare for pouring the concrete columns.
LIONS/LSU CLINIC BLDG 7th FLOOR RENOVATIONS:
- The contractor installed countertops for the lab furniture.
- Workers continued connecting plumbing fixtures and installing electrical conduit in the lab furniture.
FENCE REPLACEMENT PROJECT:
- Contractor poured concrete for first section of sidewalk adjacent to new fence.
LANDSCAPING/EXTERIOR:
- Facility Services completed installation of irrigation piping and sprinkler stations on the Florida Avenue and parking lot sides of the School of Dentistry Clinic Building,
- They connected control wires for last three sprinkler station valves.