MONDAY, APRIL 19, 2010

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued placing CMU block in both stairwells along Bolivar Street.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor chipped out the fuel line penetration on the 7th Floor.
  • Crews began construction of the temporary elevator shaft wall and installed temporary walls in the bookstore.

LIONS/LSU CLINC BLDG 7th FLOOR RENOVATIONS:

  • The contractor continued installing countertops, connecting gas pipes, and terminating data ports to the new lab furniture.

FENCE REPLACEMENT PROJECT:

  • The contractor continued to set forms for the final section of sidewalk along Florida Avenue extending to the horseshoe.

DENTAL SCHOOL NORTH FIELD GRADING:

  • The contractor continued grading work for the new visitor parking lot and re-contouring the remainder of the field.

LANDSCAPING/EXTERIOR:

  • Facility Services completed 80% of vegetation removal on the Florida Avenue side of the School of Dentistry Clinic Building.