ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued laying CMU block in both stairwells along the Bolivar Street side of the building.
  • Sprinkler heads were repaired in the Tiger Room.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor began installing underground electrical conduit near the old switchgear.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor chipped out the floor for the fuel line penetration on the 6th Floor and the floor penetration for the switchgears bus duct in the bookstore.
  • Crews continued building the temporary elevator shaft wall.

LIONS/LSU CLINIC BLDG 7th FLOOR LAB RENOVATIONS:

  • The contractor continued installing countertops, connected gas pipes, and terminated data ports for the lab furniture.

LIONS/LSU CLINIC BLDG 8th FLOOR RENOVATIONS:

  • The contractor completed installing light fixtures in the main lobby area.

FENCE REPLACEMENT PROJECT:

  • The contractor continued to set forms for the final section of sidewalk along Florida Avenue leading to the horseshoe.

DENTAL SCHOOL NORTH FIELD GRADING:

  • The contractor continued grading the field and setting new elevations.

LANDSCAPING/EXTERIOR:

  • Facility Services completed vegetation removal on the Florida Avenue side of the School of Dentistry Clinic Building and began grading.